On January 23, 2019, Chengdu Irish Charms Optoelectronics Co., LTD. (referred to as "Chengdu Irish Charms"), located in the high-tech West District of Chengdu, ushered in an important moment since the start of construction: the first mask version of the first G11 generation mask version project in China successfully rolled off the line.
2019-01-23 Irish Charms Optoelectronics 23
On November 15, 2018, in commemoration of the 50th anniversary of the invention of liquid crystal display technology, the 14th China International Display Conference (CIDC 2018) with the theme of "Liquid Crystal changes human life" was held in Wuzhou Hotel. Irish Charms Optoelectronics, as an innovative enterprise to promote the localization of upstream materials for display Irish Charms in China, was invited to participate, and Lin Wei, executive deputy general manager, delivered a wonderful report on the theme "Application of mask technology in the field of high generation panels" at the conference.
2018-11-15 Newway 11
At 8:40 am on September 27, the phase I equipment of G11 high generation mask edition project of Chengdu Irish Charms Optoelectronics Co., LTD. (referred to as "Chengdu Irish Charms"), located in the high-tech West District of Chengdu, moved smoothly into the high-grade purification plant. Marking the first G11 photomask project in China ushered in an important milestone of completion and production, the next will enter the intensive equipment installation and commissioning stage, a step closer to the official production of G11 photomask products.
2018-09-27 Newway 12
On July 23, 2018, as the last piece of roofing concrete slab was finished pouring, the main workshop of G11 mask plate production line of Chengdu Irish Charms Optoelectronics Co., LTD. (hereinafter referred to as "Chengdu Irish Charms") located in Chengdu High-tech West District was successfully capped. This marks the first domestic G11 mask version project construction has taken a solid step forward, is about to enter the plant purification and decoration stage, is expected in September the main equipment into the factory installation and commissioning.
2018-09-07 Newway 19